Eligibility of Construction Equipments
under Project Imports
Plant Site Verification Certificate must be Submitted
for Finalization of Project
[CBEC Circular No. 49 dated 4th November
2011]
Subject: Eligibility of
assessment of construction equipments under Project
Imports Regulations (PIR), 1986 – Instructions.
References have been
received that divergent practice are being followed by field formations
regarding assessment of import of construction equipments
required for the initial setting up of a unit, for a specified project under
Customs Tariff Heading No. 98 01 (Project Imports).
2. The issue has been examined by Board in view
of decision of Hon’ble Supreme Court in the case of
Commissioner of Customs, Mumbai vs. M/s. Toyo Engineering India Ltd., 2006(201)
ELT 513 SC where in the it has been observed; “The goods imported by the respondent such as hydle
truck cranes, excavator, shovel loader, truck, forklift truck, power
generators, diesel welder, welding rectifier, containers tools and tackles instruments,
level Nako with tripod and theodlite
Nako with accessories & tripod would certainly be
auxiliary equipments which would help in the initial
setting up of the industrial plant.” It is also observed by Hon’ble Apex Court in Punjab Power State Electricity Board
[1997(91) ELT 247(SC), “that the
vehicles, which are used in the shifting of the transformers would not
constitute integral activity of the project”.
3. In view of above said decisions it is
clarified that the scope of the items eligible for import under the Project
Import Regulations 1986, shall cover construction equipments as auxiliary equipment; if essentially required for initial setting up or substantial
expansion of registered projects.
4. Further it is clarified that the construction equipments may be permitted to be transferred to other
registered project under CTH 9801, after completion of its intended use, on
recommendations of sponsoring authority.
5. It is also clarified that ‘Plant Site
Verification Certificate’ (PSVC) required to be submitted for finalization of
project as per Circular No. 14/2006-Cus F.No.
528/9/2006-Cus (TU) shall also incorporate the details of construction equipments imported and used for the project, to ensure
proper utilization of goods imported.
6. These instructions should be brought to the
notice of all the concerned by way of issuance of instructions /trade notice.
7. Difficulty faced if any, may be brought to the
notice of the Board.
F.No.528/14/2008-Cus (TU)