Custodian should
Provide Computer Systems in AC Environment to Customs, Says CBEC
Subject: Provisions relating to EDI infrastructure under the “Handling
of Cargo in Customs Areas Regulations, 2009”.
F.No.450/55/2008-Cus.IV
[Ref: CBEC Circular No. 21 dated 04.08.2009]
A reference is invited to the “Handling of Cargo in
Customs Areas Regulations, 2009” (referred in short as ‘regulations’) and the
circular No.13/2009-Customs dated 23.3.2009 issued indicating the salient
features of the regulations.
2. In
Regulation 5(1)(j), the requirements of adequate
Air-conditioned space and other facilities such as power back up, hardware,
networking and other equipments for secure connectivity with Customs Automated
Systems and for exchange of information between Customs community partners was
specified to be provided by the applicant for custody and handling of imported
or export goods in a customs area. Further, the aforesaid requirements have
also been explained in detail in para 5.2 of the above mentioned circular.
3. In this
regard, it is clarified that in addition to the infrastructure required to be
provided as mentioned in para 5.2 of the circular No.13/2009-Customs, the
custodian shall provide networking, communication equipments, Uninterrupted
Power Supply System, computers, PCs, dump terminals, servers, printers and
other computer peripherals as may be specified by the Directorate General of
Systems. To this extent, the last line of the paragraph 5.2 of the circular
No.13/2009-Customs may be treated as modified as follows:
“5.2. As regards the requirement of the Customs EDI
Systems under Regulation 5(1)(j), the infrastructure required to be provided by
the custodian shall include the Civil and electrical infrastructure including
properly air-conditioned office space……. shall also be provided. (last line modified is as follows) In addition to the above,
the custodian would be required to undertake site preparation including civil
works, electrical works, electrical fittings, air-conditioning, etc. they would
also provide DG Set for power back up and link to the EDI Server. The
networking, communication equipments, Uninterrupted Power Supply System,
Computers/Personal Computers/Thin Clients, servers, printers and other computer
peripherals as may be specified by the Directorate General of Systems shall
also be provided by the custodian.”
4. Any
difficulties in implementation of these Regulations may be brought to the
notice of the Board immediately.