Subject: Amendment To Facility Notice No. 79/2009 Dt 01.10.2009 – reg. procedure to be followed in case of
EPCG Scheme.
Facility Notice No. 79/2009 issued vide F. No. S/26-Misc-86/08 EPCG JCH dated 01.10.2010 is
being amended to align with the new guidelines regarding monitoring of export
obligation against EPCG Licences issued by CBEC vide Circular No. 05/2010-Cus. dt 16.03.2010 as follows :
In Para 2,
at the end of sub para 2.2, the
following new sub para should be added:
“A random verification for some of the
authorization issued under EPCG scheme and registered with this port shall be
carried out to check
the correctness of the address shown on the authorization, preferably through
Central Excise division”.
Para 3:-
Post Import Compliance:
In para 3.1, the following line should be added at
the end of para 3.1:-
“Further, the correctness of the installation
certificate, which are issued by the Chartered
Engineer shall be verified on random basis through the jurisdictional Central
Excise divisions”.
At the end
of Para 3.3, the following sub para
should be added:
“In case the export obligation of first block is
verified and found satisfactory, the Export Obligation Discharge Certificate
issued by DGFT after the end of 2nd block may be accepted without further
verification unless there is specific intelligence suggesting need for detailed
verification”.
F. No.
S/26-Misc- 86/08 VIIG JNCH